Carbone v Fowler Homes Pty Ltd [2024] NSWCA 192
The NSW Court of Appeal has delivered a key judgment with significant implications for builders and contract drafters. In Carbone v Fowler Homes Pty Ltd, the Court confirmed that a nominal liquidated damages clause (e.g. $1/day) does not prevent owners from seeking general damages for construction delays.